We finished up the framing on the deck last Saturday. Monday we had a framing inspection because it is a low level deck. Tuesday we installed the double tiered fascia, and the deck boards. Wednesday we cut in the borders and built all the rail sections. Thursday we got rained out. Friday we finished up the railings and power washed the deck and cleaned up the jobsite
Screwed down the 5/4 cedar deck boards

Flashed the ledger board Double tiered fascia

Cedar 2x4 railing with Fortress 3/4 round balusters,

post caps and skirts, and center squash blocks

Single picture frame border on the deck and steps with the fascia dropped under the the border

Two levels on this deck - matching the houses, drop down living room doorwall Four foot wide steps with tiered fascia matching the deck All Done

We are off to Shelby Township for a Correct Deck CX composite job, I will post the design in a few days
Thank You..... Bayn